Vertical Construction Has Begun!

xtremecoasters

Thursday, November 29, 2012 4:38 PM

Anybody got a link to that FB page...

+0

StealthPirate07

Thursday, November 29, 2012 4:39 PM

I am surprised that they are putting in those pieces before the elements that will be below the lift hill.

+0

JuggaLotus

Thursday, November 29, 2012 5:07 PM
JuggaLotus's avatar

The loop isn't below the lift hill. It's next to it.

And the lift is generally the first thing to go up because the other lift hill work can be done while the rest of the essentially bare track can be laid.


Goodbye MrScott

John

+0

xtremecoasters

Thursday, November 29, 2012 6:01 PM

The loop actully goes under the lift hill twice. Once on the entrance and once on the exit.

Looks like its going to be a big mess of supports and track.

Last edited by xtremecoasters, Thursday, November 29, 2012 6:07 PM
+0

Tennessee_CP_Fan

Thursday, November 29, 2012 7:16 PM

I don't think there is any need for concern on Adena's decisions on erecting a coaster....this isn't their first rodeo....


Nick

+0

Coasterkyle

Thursday, November 29, 2012 8:18 PM

B&M sends instructions on how the ride should be erected in what order. I saw this when I saw a (eaither Discovery or Travel Channel) show, When Six Flags was constructing Tatsu.


08 -Thunder Canyon, 09 - Maverick, 10 - Mean Streak, 11 & 12 - Mean Streak ATL, 13 - Maverick TL

+0

Maverick00

Thursday, November 29, 2012 8:26 PM
Maverick00's avatar

I know for Leviathan, the last piece was right before the brake run.


Enjoy the rest of your day at America's Rockin' Roller Coast! Ride On!

+0

djDaemon

Thursday, November 29, 2012 10:00 PM
djDaemon's avatar

xtremecoasters said:
The loop actully goes under the lift hill twice. Once on the entrance and once on the exit.

Untrue.


Brandon

+0

CPfan1976

Thursday, November 29, 2012 10:15 PM

extremecoasters said:


Anybody got a link to that FB page...

http://www.facebook.com/pages/OkOkAlright-I-must-admit-Cedar-Point-...tos_stream

BTW, I'm pretty confident that the owner of that page is a construction worker, if not it could be Matt Ouimet doing the best marketing campaign for CP. They've been allowed to be there for the blasting of Space Spiral, on site during construction, and there for the delivery of the first Gatekeeper track pieces so they have knowledge ahead of time for scheduled deliveries. They're not trespassing when taking those pics, they're on the "inside".

+0

xtremecoasters

Thursday, November 29, 2012 10:29 PM

djDaemon said:

xtremecoasters said:
The loop actully goes under the lift hill twice. Once on the entrance and once on the exit.

Untrue.

Ok, so it goes under the supports for the lift hill, not directly under the lift track.

+0

TTD 120mph

Thursday, November 29, 2012 10:33 PM
TTD 120mph's avatar

^^^That made the designer nerd in me squeal. I love design layouts. :)

Last edited by TTD 120mph, Thursday, November 29, 2012 10:33 PM

-Adam G- The OG Dragster nut

+0

Maverick00

Thursday, November 29, 2012 10:37 PM
Maverick00's avatar

They were also there for the building of Luminosity.


Enjoy the rest of your day at America's Rockin' Roller Coast! Ride On!

+0

Tennessee_CP_Fan

Thursday, November 29, 2012 10:46 PM

So according to that layout, the queue for the right side seats of the trains will go under the track? I guess they have to cross it somehow, I just had never considered it....


Nick

+0

Maverick00

Thursday, November 29, 2012 11:26 PM
Maverick00's avatar

So it looks like the queue will be between GateKeeper and Wicked Twister. I thought it would be near the transfer track.


Enjoy the rest of your day at America's Rockin' Roller Coast! Ride On!

+0

MillenniumSpork

Thursday, November 29, 2012 11:54 PM
MillenniumSpork's avatar

CPfan1976 said:

extremecoasters said:


Anybody got a link to that FB page...

http://www.facebook.com/pages/OkOkAlright-I-must-admit-Cedar-Point-...tos_stream

BTW, I'm pretty confident that the owner of that page is a construction worker, if not it could be Matt Ouimet doing the best marketing campaign for CP. They've been allowed to be there for the blasting of Space Spiral, on site during construction, and there for the delivery of the first Gatekeeper track pieces so they have knowledge ahead of time for scheduled deliveries. They're not trespassing when taking those pics, they're on the "inside".

Who says it's just one person? Haha.


2010: Millennium Force & Mantis
2011: Raptor
2012: Raptor, Sky Ride and Wicked Twister
2013: Co-Team Leader of Sky Ride
2014: Supervisor of Slingshot/Skyscraper

+0

xtremecoasters

Friday, November 30, 2012 4:06 AM

CPfan1976 said:

extremecoasters said:


Anybody got a link to that FB page...

http://www.facebook.com/pages/OkOkAlright-I-must-admit-Cedar-Point-...tos_stream

BTW, I'm pretty confident that the owner of that page is a construction worker, if not it could be Matt Ouimet doing the best marketing campaign for CP. They've been allowed to be there for the blasting of Space Spiral, on site during construction, and there for the delivery of the first Gatekeeper track pieces so they have knowledge ahead of time for scheduled deliveries. They're not trespassing when taking those pics, they're on the "inside".

Thanks...yea it looks pretty organized.

+0

djDaemon

Friday, November 30, 2012 11:07 AM
djDaemon's avatar

Maverick00 said:
So it looks like the queue will be between GateKeeper and Wicked Twister. I thought it would be near the transfer track.

Keep in mind that a lot may have changed since those plans were created. In fact, I believe those plans were created before the decision was made to remove Space Spiral.


Brandon

+0

davidw

Friday, November 30, 2012 1:24 PM
davidw's avatar

looks like we have a new crane

+0

MForce10

Friday, November 30, 2012 2:56 PM

Tennessee_CP_Fan said:
So according to that layout, the queue for the right side seats of the trains will go under the track? I guess they have to cross it somehow, I just had never considered it....

Firehawk at KI has a similar setup. One half of the queue goes under.

+0

vwhoward

Friday, November 30, 2012 3:04 PM
vwhoward's avatar

^X-Flight at SFGA has the left side of the train going under the station. Just before that point, you pick which side you want to ride.

Last edited by vwhoward, Friday, November 30, 2012 3:05 PM

Joe
Eat 'em up, Tigers, eat 'em up!

+0