So when did they say they were going to begin footers for GK? Was it supposed to be early September?
As stated at the announcement Q&A, footer work will get underway around October 1st.
Brandon
@dJ - Alright.
Based on the video, it seems like this whole month will be dedicated to destroying SS and other prep work, while october is the month for footers and the actual track delivery. He said we wouldn't see vertical construction until November, which is a bit of a shame, but I'm sure that construction will be visible via the webcams and Becca's blog.
IIRC, They said Space Spiral gone by the end of September, Footers begining in October, Steel delivery around mid-October.
884 Coasters, 35 States, 7 Countries
http://www.rollercoasterfreak.com My YouTube
Week 4 (8/27/12 - 9/2/12) time lapse has been added: http://www.youtube.com/watch?v=mhlvZhU6x1c
But I do like that Aaronosmer put the date on his. I have already lost track of when Week 2 was. Could you add that to the first post on your next update?
I am a bit surprised that the tree lovers are not screaming. Maybe having the lake now visible makes it OK to cut the trees down?
Sause said:
...did those trees over by the beach really serve a purpose except further blocking the lake where DT did not?
Have you ever seen a tree? Specifically, of the deciduous variety?
No? Ahh, ok then - that explains it. ;)
Deciduous trees often do not have branches so close to the ground that they block the view for people under 14' tall.